Building 2

Building 2 Week 1 Painting

Building 2 Week 1: Upstairs Plastic Barrier Wall Up all week, Lead Abatement, Painting Entrance side of condos. 4/24 Monday 8:00 am – 12:30 pm Staging of Building 2 Upstairs: Workers install plastic barrier wall enclosing and protecting walkway side of the building. 12:30 pm -3:30 pm Lead Abatement. Condos will NOT be accessible during [...]

By |2017-04-29T18:13:35-10:00April 29th, 2017|, |0 Comments
Go to Top